PROJECTS: EPISODE 2 - HYDERABAD METRO RAIL LIMITED

 HYDERABAD METRO RAIL LIMITED

Hyderabad Metro is a mass rapid transit system in Telangana, India.

  • Project Name: Hyderabad Metro Rail Project.
  • Owner: Hyderabad Metro Rail Limited, Govt. of Telangana.
  • Operator: L&T Metro Rail (Hyderabad) Limited.
  • Project Type: Mass Rapid Transit System (MRTS)
  • Planned Metro Rail Network: 188 km (7 Lines)
  • Operational Network: 69.21 km
  • Project Cost: INR 18,800 Crore (Phase-I)
  • Funding Pattern: PPP Mode
  • Start Date of Operation: 29 November 2017

Hyderabad Metro Phase I

Major Contractors

  • Larsen & Toubro (L&T):  Concessionaire for construction, operational & maintenance of Hyderabad Metro Phase I under PPP mode
  • Thales Group: Supply of Signaling & CBTC Technology (Rs 740 crore)
  • Hyundai Rotem: Supply of Rolling Stock 57 trains (171 cars). (Rs 1,800 crore)

Line 1 (Red Line): Miyapur – LB Nagar (via Ameerpet)

  • Route length: 29.21 km (Operational)
  • Total Stations: 27 (All elevated)
  • Stations: Miyapur, JNTU College, KPHB Colony, Kukatpally, Balanagar, Moosapet, Bharat Nagar, Erragadda, ESI Hospital, SR Nagar, Ameerpet, Punjagutta, Irrum Manzil, Khairatabad, Lakdikapul, Assembly, Nampally, Gandhi Bhavan, Osmania Medical College, Mahatma Gandhi Bus Station (MGBS), Malakpet, New Market, Musarambagh, Dilsukhnagar, Chaitanyapuri, Victoria Memorial, LB Nagar.
  • Interchange Stations: Ameerpet (Blue Line), MGBS (Green Line)
  • Connected Depot: Miyapur

Line 2 (Green Line): JBS – Falaknuma (via MG Bus Station)

  • Route length: 15.02 km (Operational-11 km, Under construction-4.2 km)
  • Total Stations: 16 (All elevated)
  • Operational Stations: JBS, Parade Grounds, Secunderabad, Gandhi Hospital, Musheerabad, RTC Cross Roads, Chikkadpally, Narayanguda, Sultan Bazar, Mahatma Gandhi Bus Station (MGBS).
  • Under construction Stations:  Salarjung Museum, Charminar, Shalibanda, Shamsher Gunj, Jungametta, Falaknuma.
  • Interchange Stations: MGBS (Red Line), Parade Grounds (Blue Line)
  • Connected Depot: Falaknuma

Line 3 (Blue Line): Raidurg - Nagole

  • Route Lenth: 29 km (Operational)
  • Total Stations: 23 (All elevated)
  • Stations: Nagole, Uppal, Survey of India, NGRI, Habsiguda, Tarnaka, Mettuguda, Secunderabad, Parade Grounds, Paradise, Rasool Pura, Prakash Nagar, Begumpet, Ameerpet, Madhura Nagar, Yusuf Guda, Road No 5 Jubilee Hills, Jubilee Hills Check Post, Pedamma Temple, Madhapur, Durgam Chervu, HITEC City, Raidurg.
  • Interchange Stations: Ameerpet (Red Line), Parade Grounds (Green Line)
  • Connected Depot: Uppal

Hyderabad Metro Phase II

Line 1 (Red Line) Expansion:

  • Miyapur - Patancheru via BHEL (15 km)
  • LB Nagar - Hayath Nagar (7 km)

Line 2 (Green Line) Expansion: JBS - Alwal (8 km)
Line 3 (Blue Line) Expansion: Nagole - Shamshad RGI Airport via LB Nagar - Falaknuma (28 km)
Line 4: Raidurg - Shamshad RGI Airport via Gachibowli (30 km)
Line 5: Miyapur – Lakdi ka pul via Gachibowli–Tolichowki (20 km)
Line 6: Tarnaka – ECIL 'X' Roads (7 km)


Popular posts from this blog

TECHNOLOGY : EPISODE 12 - FERRO CEMENT

ENGINEERING LESSONS - EPISODE 8 - DESIGN FORCES IN METRO BRIDGES