ENGINEERING LESSONS: EPISODE 22 - OPTIMIZED LIVE LOADED VIADUCT BRIDGES

Image
  OPTIMIZED LIVE LOADED VIADUCT BRIDGES In the Present state of the art, a Bridge Engineer usually optimize the design component in four ways. This article will discuss about the possibility to optimize the design loads with  Effective Live Load Concept. Problem Statement: Criteria 1: The vehicle volume in the road is majorly classified into two types namely passenger vehicle segment & commercial vehicle segment. Around 90% of vehicles on road are passenger vehicle segment and only 10% of the vehicle is under commercial vehicle segment. Commercial vehicles are higher weight compared to passenger vehicles. But a Bridge Engineer is pulled to compulsion in designing the bridge for the governing vehicle load that is a commercial vehicle, even though their volume is less compared to a passenger vehicle. As per Indian scenario, IRC Class AA & A are far higher than the normal vehicles. Criteria 2: In a densely populated city there will be always an alternative route to reach a destiny

ENGINEERING LESSONS: EPISODE 21 - INNOVATIVE IDEA TO REDUCE THE METRO VIADUCT HEIGHT

Image
Innovative Idea to reduce the Metro Viaduct Height Usual metro rail viaduct’s deck width will be in the range of 8.8 to 10.5m, which can be easily accommodated within the 1st lane of underneath traffic. If the 1st lane on both side of the underneath traffic is restricted with height constrains for vehicular traffic (say 3.0m), then the vertical profile can be lowered. The vehicle's with height greater than the restricted height can use the other lanes. This will ultimately help in saving the pier quantity w.r.t to concrete & steel. This will also help in reduction of design forces for the substructure and foundations; since the height of pier is reduced. Constraints in implementing the Idea In cities where the alignment has to cross much road intersection, this ideology will not provide sufficient head room clearance. Because in such case the vertical profile need to be lower/rise; but the allowable gradien

HEALTH : EPISODE 2 - ULTRA MIND

Image
 EPISODE 2 - ULTRA MIND This Episode discusses about how effectively we can utilize the Alfa Brain, in our day to day life. The method is one of the well known method practiced around 60 years, Thou we have a more historical heritage methods available for centuries in India. This one is available in audio/video version and explained in simple words, so it is added to kick start the series.  01 - The Amazing Power of Your Mind 02 - A Special Level of Mind 03 - The Importance of Mental Housecleaning 04 - Achieving Your Goals with the Mental Techniques 05 - Powerful Problem-Solving Techniques at Work 06 - Powerful Problem-Solving Techniques at Home 07 - Mental Discipline - How to Be More Like a Genius 08 - Using Your Mind to Improve Your Health 09 - Gaining Habit Control with the Mirror of the Mind 10 - Creating Your Own Mental Laboratory 11 - Discovering Your Ability for Clairvoyance and ESP 12 - Glimpses of a Future 13 - Alpha Reinforcement Exercise  14 - The A

HEALTH : EPISODE 1 - INTRODUCTION

Image
 EPISODE 1 - INTRODUCTION ‘Health is wealth’ is a world-famous proverb concerning health. A healthy body is defined as the overall ability of the body to function well. It includes the physical, mental, emotional, and social health of all individuals. A healthy body holds major components that aid the functioning of the body. The first essential component is the state of physical health. Physical health refers to the state of being physically healthy devoid of any illness or diseases. When one maintains good physical fitness, they tend to have an extended lifespan.  The next health component is the mental health or mental well-being. Mental health refers to a state of emotional and psychological well-being of the individual. A person’s mental well-being impacts their emotions and behavior in handling situations. The best-recommended way to maintain mental health is by staying positive and meditating. To perform well and remain active in our  professional life we must stay fit and fine.

ENGINEERING LESSONS: EPISODE 20 SAMRUDDHI EXPRESSWAY VUP COLLAPSED

Image
 EPISODE 20 SAMRUDDHI EXPRESSWAY VUP COLLAPSED Place  Maharashtra's  Samruddhi Expressway,  (Nagpur-Mumbai Super Communication Expressway) Package -3 Date of Incident: 7/1/2021 Fatality: Officially No Contractor : NCC Reason:  VUP collapsed due to over dumping of green concrete concentrated to a portion over the slab, which leaded to load concentration over a point, as due to which the ground support system failed to carry the load, eventually lead to collapse.

ENGINEERING LESSONS EPISODE 19 GARUDA VARADHI FLYOVER GROUND SUPPORTING FRAME COLLAPSED

Image
 EPISODE 19 GARUDA VARADHI FLYOVER GROUND SUPPORTING FRAME COLLAPSED Date of Incident: 25/1/2021 Contractor: AFCONS Fatalities  - Officially NO About the Incident: Usually due to some site constraints, some spans will be casted with Ground Support System where LG Launching is not possible,  In the Incident, there was a down Gradient from the pier to pier levels, even they used the standard Ground Support System which is normally used in Segment/Viaduct Construction. Due to improper interlocking with the  end tower with pier might be the reason of the Span Collapse. Video of the Incident All Episodes of Engineering Lessons

PROJECTS : CHAPTER 9 PUNE METRO

Image
 CHAPTER 9 PUNE METRO Project Name: Pune Metro Rail Project Owner: Maharashtra Metro Rail Corporation Limited (Maha Metro) Project Type: Mass Rapid Transit System (MRTS) Project Cost: 24,478 Cr Funding Pattern: Govt. of India, Maharashtra Govt. and Foreign Funding Institutions Completion Target: 2021 Corridor I: PCMC – Swargate Total Length: 16.589 km Total Stations: 14 (Elevated -9, Underground-5) Station Names: Pimpri Chinchwad Municipal Corporation (PCMC), Sant Tukaram Nagar, Bhosari, Kasarwadi, Fugewadi,Dapodi, Bopodi, Khadki, Range Hill, Shivajinagar, ASI, PMC, Budhwar Peth, Mandai, Swargate. Corridor II: Vanaz – Ramwadi Total Length: 14.665 km Total Stations: 16 (All Elevated) Station Names:Vanaz, Anand Nagar, Ideal Colony, Nal Stop, Garware College, Deccan Gymkhana, Sambhaji Park, PMC,Civil Court, Mangalwar Peth, Pune Railway Station, Ruby Clinic, Bund Garden, Yerawada, Kalyani Nagar, Ramwadi.   Corridor III: Hinjawadi – Shivajinagar Project Cost: Rs 8,100.00 Crore Total Length: